Progress & Updates
Estimated Completion Date: Summer 2025

Land Cleared

Commenced October 1, 2024

Flooring Poured

Commenced December 18, 2024

Columns and Headers Added

Commenced January 13, 2025

Footing Poured

Commenced October 28, 2024

Block-work Commenced

Commenced December 23, 2024

Plunge Pools Excavated and Concrete Poured

Commenced January 20, 2025

Foundation Poured for Blue Fin Residents-Only Gym

Commenced January 24, 2025

Framing Completion

Commenced January 28, 2025

Roof Trusses Installed

Commenced March 6, 2025

Ice and Water Shield Installation in Progress

Commenced March 21, 2025

Roof Shingles Installation in Progress

Commenced March 30, 2025

Drywall Installation in Progress

Commenced March 31, 2025

Roof Completed

Commenced April 3, 2025

Windows Installed

Commenced April 5, 2025