Estimated Completion Date: Summer 2025
Land Cleared
Commenced October 1, 2024
Footing Poured
Commenced October 28, 2024
Flooring Poured
Commenced December 18, 2024
Block-work Commenced
Commenced December 23, 2024
Columns and Headers Added
Commenced January 13, 2025
Plunge Pools Excavated and Concrete Poured
Commenced January 20, 2025
Foundation Poured for Blue Fin Residents-Only Gym
Commenced January 24, 2025
Framing Completion
Commenced January 28, 2025
Roof Trusses Installed
Commenced March 6, 2025
Ice and Water Shield Installation in Progress
Commenced March 21, 2025
Roof Shingles Installation in Progress
Commenced March 30, 2025
Drywall Installation in Progress
Commenced March 31, 2025
Roof Completed
Commenced April 3, 2025
Windows Installed
Commenced April 5, 2025
Interior Doors Installation in Progress
Commenced May 10, 2025
Exterior Columns in Progress
Commenced May 12, 2025
Kitchen Island and Cabinets Installation in Progress
Commenced June 11, 2025
Paving Commenced
Commenced May June 12, 2025